The Early Years     |     1923 - 1929     |     1930 - 1939     |     1940 - 1949     |     1950 - 1959     |     1960 - 1969     |     1970 - 1979     |     1980 - 1989     |     1990 - 2002     |     80 Years     |     Museum     |     Time Capsule     |     Video of Eskom's History     |     Heritage Home


sh_taaibos.gif (1112 bytes)


[ SUPPLY AREA | STAFF | FACILITIES | TIMELIME | TECHNICAL DETAILS | COMMISSIONING OF PLANT | DESCRIPTION OF PLANT | BOILER HOUSE | COAL PLANT | COOLING TOWERS | WATER | SWITCHGEAR | CONTROL ROOM | TRANSFORMERS | WORKSHOPS | MOTHBALLING | DECOMMISSIONING ]

Taaibos and Highveld power stations each had a capacity of 480MV supplied by 8 turbo generators of 60MW. They were to be the largest and most up-to-date power stations in the Eskom system at that time. They were intended to be the last power stations in the Vereeniging area because of the limited availability of coal.

The two power stations, Taaibos and Highveld, are situated 0.8 kilometres apart in the Northern Orange Free State, approximately 32 kilometers south of Vereeniging. They formed part of the Rand and OFS Undertaking of the Electricity Supply Commission (Escom).

PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION

Taaibos Power Station Taaibos Power Station

Taaibos power station in foreground

SUPPLY AREA
The original licence for the Rand and OFS Undertaking supply area consisted of a narrow strip on either side of the Witwatersrand extending from Nigel to Randfontein. It also included an area of approximately 5km radius around Heidelberg, and a small area around Vereeniging.

By 1947, the Rand and OFS Undertaking supplied an area of about 103 600 square kilometres and included 4 major gold mining areas, i.e. Witwatersrand, the far West Rand, Klerksdorp and the Orange Free State. The boundaries of the supply area were that of Thabazimbi in the north, Mafeking (Mafikeng today) in the west, Winburg in the south and Witbank in the east.

By 1975 the Rand and OFS Undertaking was extended to 261 000 square kilometres. It was extended to cover a further 250 000 square kilometres by 1979, with areas ranging from the Zimbabwe (then Southern Rhodesia) border in the North, to the Lesotho border in the south, and from Standerton in the east to the Botswana border in the west.

In 1983, this changed when Eskom decided to amalgamate the separate undertakings into a national grid system. This became a reality in 1984.


RETURN TO TOP OF PAGE    Go to the Top of the page


STAFF

By 1963, when both Taaibos and Highveld were running at full capacity there were 916 people working at the two stations. Eskom employed 160 white employees and 300 black employees at Taaibos. At Highveld 156 white employees and 300 black employees were employed.


RETURN TO TOP OF PAGE    Go to the Top of the page


FACILITIES 

At the time that the two stations were being constructed all residents were subjected to ethnic segregation according to the law of the country.

PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION

The white employees were housed in two villages - one for each power station. They shared recreational facilities, which included a recreation centre, swimming pool, and sports fields (rugby, football and tennis). The residents of Taaibos and Highveld villages developed a strong sense of community. Competitiveness between the two villages emerged in social events and on the sports field. Aerial view of the townships

Aerial view of the townships

The recreation club included an alcohol-free canteen, an amateur dramatic society, weekly film shows, a library and badminton and an active Cub and Scout group. The province established a satellite library. Books arrived on a rotational basis from the Kroonstad and Bloemfontein main libraries.

Accommodation for black employees was arranged so that those from the same tribe were grouped together. Whenever possible, those performing similar work were accommodated together. The black housing compounds were built predominantly for single men, although some included quarters for those who were married.

PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION
House in the suburbs

A house in one of the residential townships

The two stations were totally self-sufficient providing accommodation for employees - single dwelling units, boarding houses and single quarters, a sewage plant and a potable water purification system. The community also had its own horticultural nursery, a convenience store, medical and dental facilities and a post office. The post office was registered as the Kragbron Post Office, which later became the collective name of the two power stations. The province later built a dual medium primary school for the children of residents of the two stations. The power station managers were responsible for the running of the villages.
In 1963 it was proposed that the Kragbron United Community Chapel be built in order to serve as a multi-congregational church for the community of the two power stations. The church was to represent the Anglicans, Presbyterians, Methodists and Catholic churches. A local farmer donated a piece of land on which to build the chapel and funds were raised for its construction. However the project never materialised.

RETURN TO TOP OF PAGE    Go to the Top of the page


TAAIBOS TIMELINE OF HISTORY (1947 - 1963)

1947 In May 1947 the Commission was granted a licence for the Greater Rand Extension Undertaking to supply electricity within an area of approximately 41 440 square kilometres of Transvaal, OFS and the Northern Cape Province.
1949 It was decided to build a new power station to be known as Taaibos. The name was taken from the nearby Taaibosspruit that flowed into the Vaal river. The station would be situated on a site adjoining the Clydesdale Colliery near the Coalbrook Colliery in the Northern OFS, and the primary objective of the station would be to provide additional power for mining and industry in the supply area. T he chairman of Eskom at the time was Albert Michael Jacobs.
1950 The estimated cost of the station was 15 959 000, and it was expected to be in operation by 1954.
1951 Work on site commenced in April.
1952 By April 1952 the site preparation was complete, but a shortage of steel delayed the construction of the main buildings. Work was in progress for the Vaal river pump house and pipeline. The first turbo-generator was expected to be ready to deliver service by the second half of 1954. The estimated cost had increased to 18 313 000,
1953 By early 1953 work had begun on the erection of the steelwork for the boiler house. The laying of the railway tracks and accommodation construction was in progress. The estimated cost was again revised to 19 300 000.
1954 Dr Johannes Theobald Hattingh was Chairman of Eskom when Taaibos power station began operation. In March 1954 the 132kW switchyard was brought into use. The first set in the power station was run up on the 27 November 1954 and was placed in commercial service from the 9 December 1954.
1955 A decision was made to extend Taaibos power station by adding one further 60 000kW set and corresponding boiler to make a total of eight. The additional set was expected to be in service by the end of 1957. The number 2 turbo-generator with its boiler plant was brought into commercial service in April, and the third in October.
1956 The number 4 set with its boiler was commissioned at the beginning of March 1956.
1957 In April, a further 60 000kW set was commissioned
1958 By 1958 Taaibos was developed to its full capacity permitted by the available resources. Taaibos achieved a record output from a single power station of 2 807 million units for the year. This surpassed the previous record of 2 762 million units sent out from Klip power station in 1952.
1960 Disaster at Coalbrook North Colliery
1963 Total capital cost was approximately 46 400 000.00 On the 8th November 1963 the Honorable Minister AE Trollip visited both Taaibos and Highveld power stations at the invitation of Dr and Mrs RL Straszaker.

RETURN TO TOP OF PAGE    Go to the Top of the page


TECHNICAL DETAILS

•Total station electrical capacity 480 000kW
•Total boiler capacity 4 640 000lb/hour
•Steam consumption per kWh generated 9.3lb
•Approximate calorific value of coal 8 750 BTU/lb.
•Overall thermal efficiency on units sent out 26.0 %
•Heat rate on units sent out 13 110 BTU/kWh
•Coal Consumption per unit sent out 1.498 lb.

RETURN TO TOP OF PAGE    Go to the Top of the page


COMMISSIONING DATES OF THE PLANT

Turbo Generator Date
         1 November 1954
         2 April 1955
         3 October 1955
         4 March 1956
         5 April 1956
         6 October 1956
         7 December 1956
         8 December 1957

RETURN TO TOP OF PAGE    Go to the Top of the page


GENERAL DESCRIPTION OF THE PLANT

Turbine House

Eight 3 cylinder reaction type turbines with generators rated at 60MW. (70 600kVA at .85 power factor) manufactured by CA Parsons and Co.

•Steam conditions at turbine stop valve: 600lb/sq.in at 825 F
•Speed 3 000 rpm. With geared exciters at 1 000 rpm
•Generators air cooled with two fans each rated at 410hp
•Condensers: Cooling surface 60 000sq. ft.
•Circulating water flow 48 000 gallons / minute
•Circulating water pump motor 1600hp 490rpm
•Length of Turbine House 762 feet

 

 

 

PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION

RETURN TO TOP OF PAGE    Go to the Top of the page


BOILER HOUSE

Eight Babcock and Wilcox pulverized-fuel boilers, bi-drum with pendant superheaters and tangent tube furnaces.

•Continuous rating 580 000lb/hour
•Outlet pressure 630lb/sq.in.
•Outlet temperature 825 F
•Fully automatic combustion control
PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION
coal pulverizing mills
Four coal pulverizing mills per boiler, one as a standby, each driven by 130hp motor. Capacities of each mill 14 tons per hour.
Boiler Feed pumps: Capacity 700 000 lb/hour each. Driven by 1 290hp motor. Standby steam feed pumps to dams at the east of the station.
•Length of boiler house 654 feet
•Height of boiler house 158 feet
•Ash plant Babcock & Wilcox hydro-jet system
•Each boiler produces approximately 8 tons per hour
•Ash pumped to dams to the east of the station

RETURN TO TOP OF PAGE    Go to the Top of the page


COAL PLANT

Coal was obtained from the Clydesdale Colliery, and delivered by overland belt conveyer 5 600 feet long to station coal staiths, with a storage capacity of 24 000 tons.
•Capacity of conveyor 650 tons/hour
•Belt 42 inches wide
•Speed of conveyor 400 feet/minute

RETURN TO TOP OF PAGE    Go to the Top of the page


COOLING TOWERS

PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION

Taaibos Power Station
Six Bradford-type by LG Mouchel & Partners, Ltd. Dimensions:
•Height above cill 297 feet
•Height of water inlet 31 feet
•Internal dimensions
 Top  136 feet
 Throat  105 feet
 Cill  204 feet
•Capacity 3 000 000 gallons/hour
•Approximate temperature drop 7.5C

RETURN TO TOP OF PAGE    Go to the Top of the page


WATER

Water was obtained from the Vaal river where a pump station is installed, and brought to the station by a 0.60m pipeline, 22.5km long. Storage reservoirs at the station had a capacity of 6 000 000 gallons. The capacity of pumps and pipelines were approximately 6 600 gallons per minute. The pumps were remotely controlled from the power station switch operating room.


RETURN TO TOP OF PAGE    Go to the Top of the page


SWITCHGEAR

The main station busbars were outdoor strung-type, energized at 132kV. 132kV switchgear connected to the duplicate busbars comprised BTH bulk-oil type with a rupturing capacity of 3 500MVA. The oil capacity of each breaker was 2 300 gallons.

Each generator was connected to the 132kV busbars through a generator transformer with a step-up ratio of 11/132kV and a generator circuit breaker.

Outgoing from the 132kV busbars were nine feeders:
•Scafell (6 feeders)
•Vierfontein
•Virginia
•Highveld

Interconnection with Vaal power station was at 88kV, from the 132kV busbars though two 132/88kV coupling transformer banks.

Supply to the station auxiliaries was at 3.3kV for motors of 200hp and over, and at 380 volts for motors under 200hp.

The 3.3kV switchgear was manufactured by South Wales Switchgear, and was indoor-type oil-break with rupturing capacity of 150MVA.

The 380 volt switchgear was manufactured in South Africa and comprised mainly of contractors for motor control, with high rupturing-capacity fuses for fault protection.

SWITCH OPERATING ROOM (CONTROL ROOM)
PLEASE CLICK ON PHOTOGRAPH TO VIEW ENLARGED VERSION
Control Room
The switch operating room contained panels for the remote control of all 132kV and 88kV circuit breakers, and for main 3.3kV circuit breakers, as well as all relays for protection of generator and feeder circuits.

Communications services were also centred on the switch operating room.

The control panel suite in the switch operating room was also manufactured in South Africa.


RETURN TO TOP OF PAGE    Go to the Top of the page


TRANSFORMERS

Generator transformers were rated at 70MVA with forced air-cooling. The rating was reduced to 53MVA with natural draught cooling.

The unit transformers for the turbine and boiler auxiliaries were connected directly to the generator terminals. These were natural cooled units rated at 6.6MVA with a voltage ratio of 11/3.3kV.

The 132/88kV coupling transformers were in two groups each with an aggregated rating of 60MVA. Each group comprised three single-phase units. These transformers were equipped with delta-connected tertiary windings, delivering 3.3kV, which were used to supply general station services, including the residential properties.


RETURN TO TOP OF PAGE    Go to the Top of the page


WORKSHOPS

Mechanical and electrical workshops were equipped with machine tools and facilities for effecting normal maintenance and all but the heaviest repairs to the power station plant.


RETURN TO TOP OF PAGE    Go to the Top of the page


MOTHBALLING

The process of closing down Taaibos and Highveld power stations began in 1986. Both power stations were to be placed in reserve storage (“mothballed”) over a period of two years. A “mothballed” power station was one that could be brought back into service if necessary.


RETURN TO TOP OF PAGE    Go to the Top of the page


DECOMMISSIONING

A decline in mining and industrial activity resulted in decreased demand for electricity. Consequently, a decision was made in 1994 to decommission and dispose of Highveld and Taaibos power stations. Attempts to sell the power stations were unsuccessful. Both stations were no longer viable as operating power stations. Spare parts and the cost of operating staff would be too costly. Also, Eskom could not guarantee the demand for any electricity generated.

Staff who were employed at Kragbron either transferred to other power stations, or chose early retirement packages. As the closing down of the power station was phased over a number of years, and done in a controlled manner, the final shut-down had little affect on the surrounding community.

In 1999, five people were still working full time at Kragbron. They were to remain until the final disposal of the power stations. All storage facilities were rented to outside users to generate income.

Within the next couple of years all of the buildings will be demolished except for the offices of Taaibos.
The cooling towers will be imploded and coal staiths demolished. All equipment will be sold as parts or scrap.

The residential accommodation has been rented out by Esprop (Eskom Properties department) to non-Eskom families within the surrounding areas, and is currently running at approximately 95% occupancy.