Vaal Power Station commenced operation in January 1945 with an installed plant capacity of
66 MW. It was the first Escom station to be built in the Orange Free State [The name Escom was changed to Eskom in 1987 and the Orange Free State
is now known as the Free State]. The power station was well placed to supply
the initial requirements of the new gold deposits discovered in the Free State
in 1938. The station had been planned to have 108 MW of generating plant
installed initially, scheduled to be in operation in 1941, and to be extended
later to 400 MW, if necessary. However, delivery of equipment was delayed
and the construction programme seriously retarded by difficulties arising out
of World War II (1939-1945). When finally completed in 1953, Vaal had 318MW
of generating plant installed. (Escom Annual Reports 1938:45, 1943:12, 1945:45, 1953:89; Escom Twenty-five
Years 1923-1948:28)
Vaal Power Station was in operation for almost 45 years. It was decommissioned
during 1989, having reached the end of its economic life. Total net electricity
production amounted to 69 thousand GWh (gigawatt-hours) or sixty-nine thousand
million units. The total coal consumption was 62 million metric tons. (Escom Annual Report 1989:24 and Tables of Power Station Operating Statistics)
The increase in the price of gold in 1933, after South Africa abandoned the gold standard, led to rapid economic growth.
Establishment of the South African Iron and Steel Corporation (Iscor) in 1928, also resulted in an increase in steel-related
manufacturing industries. Even the large power resources of the Klip Power Station, started up in March 1936, were not expected
to keep pace with the ever-increasing demand for electricity. In co-operation with the Victoria Falls and Transvaal Power
Company (the VFP), Escom therefore decided in 1938, to build the Vaal Power Station. It was to be constructed on the Free State
side of the Vaal River and would be the first Escom station to be built in the Free State. As in the case of Witbank and Klip,
the station would be financed and owned by Escom, but be constructed and operated by the VFP on behalf of Escom. Like Klip, it
was also a pit-head station. The site chosen was on a coalfield that was opened up and developed to supply the fuel requirements
of the station. (Escom Annual Report 1943:12)
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| View of the Vaalbank Dam |
By contributing £124 875 towards the cost of the Vaalbank Dam, Escom
obtained the right to draw 18,5 million gallons of water per day [84
megalitres per day] from the Vaal River, thus securing an adequate supply of
cooling water for both Klip and Vaal Power Stations. (Escom Annual Report 1943:12)
The site was on the farm "Bankfontein", 9 km SSE of Vereeniging,
at Viljoensdrif in the Heilbron district of the Free State, at an altitude of
1486 metres above sea level. A plentiful supply of coal was available on
that and adjoining farms. New gold deposits were first located in the northern
Free State in 1938, and later richer deposits further south near the town
Odendaalsrus. Vaal would be strategically placed to supply the electricity
requirements of these new goldfields. The nearest mining development taking
place was about 190 km from the power station, and it was proposed to
transmit the power via 88 kV overhead lines. Approximately 291 hectare of
land was purchased including 68 ha purchased in 1940 to provide for more
ash dumps and power line networks. Construction at site had been inaugurated
by Escom's Chairman, Dr HJ van der Bijl, at a ceremony held on 23 March
1939, just over five months before World War II (1939-1945) broke out.
The original plant was expected to be in operation by 1941, but when delays in
delivery of the plant due to the war conditions became apparent, it was hoped
that the station would be in partial operation towards the end of 1943. (Escom Annual Reports 1938:45, 1940:22, 1942:6)
Orders for three 33 MW turbo-alternators and a 7 MW house set were
placed with the manufacturers in Sweden in September 1939, the month in which
war was declared. Although manufacture of the plant was completed, the war
prevented these sets from being delivered until after hostilities ended.
However, in spite of the slowing down of mining operations during the war making
the need for Vaal not quite as urgent, two 33 MW sets were nevertheless
ordered from Great Britain in 1940. (Escom Annual Report 1943:12, 1945:45)
By 1940 erection of the steel-framed generator house was in progress and two
of the cooling towers were completed. These were the tallest structures in South
Africa at the time, 320 feet [97,5m] in height. The internal diameter at
the bottom was 205 feet [62,5m] and at the top 120 feet [36,5m].
Almost the entire Escom House in Johannesburg, the new 21-storey head office
opened by the Prime Minister in 1937, could be placed inside the tower with 25m
to spare at the top. The quantity of water circulated in each tower was 4,0
million gallons per hour [5,05kl/s], twice as much as that in the towers
at Klip. The designed inlet and outlet temperatures of the water were 36°C
and 27,5°C with an atmospheric temperature of 21°C and humidity of
75%. Make-up water was taken from a pumping station below the Vaalbank Dam via a
pipeline about 6km in length. (Escom Annual Report 1940:22, 1944:46, Escom
Twenty-five Years 1923-1948:28&46)
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| Escom House |
The three main
turbo-alternators and the house sets ordered from the Swedish firm ASEA were
Ljungström sets (pr. yung-strauom (Swed)=heather river). These were radial flow
reaction turbines, invented by Birger Ljungström (1872-1948) and patented under
British Patent 7833:1907. Frederik Ljungström and others further developed the
design. The steam flow was outwards from the shaft, with blades mounted on two
wheels rotating in opposite directions. There were no fixed blades. Each wheel
was coupled to an alternator that carried half the load. An outstanding feature
was the extreme compactness of the design. The Ljungström turbine was
manufactured under licence by Svenksa Turbinfabriks Aktiebolaget Ljungström (STAL)
in Sweden, and Brush Electrical Engineering Co in England. Sets as large as 65 MW
were installed in Sweden in 1949. The Vaal radial flow sets were at that time
unique to Escom, although there were municipalities in South Africa with smaller
sets in operation. When Escom took over the West BankI Power Station at
East London in 1947, all sets at that station were Brush Ljungström sets and
Escom added another 7,5 MW set. Two Brush Ljungström 1,5 MW sets were
also in operation at King William's Town Power Station when taken over by Escom
in 1948. (Escom Twenty-five Years 1923-1948:46&48; Ljungström 1949:211-218; Auger
1965:65; Escom Megawatt No.30/1974:12; A History of Technology 1978, Vol
VII:1030; Hanks & Hodges 1988:330; McGraw-Hill Dictionary of Engineering
1997:301)
Due to the German invasion
of Denmark and Norway during the war, it became impossible to ship the sets from
Sweden, even though manufacture had been completed. Two 33 MW sets, of the
normal axial flow type, were therefore ordered from Metropolitan Vickers in
Great Britain in 1940. They were safely delivered by the British Merchant Navy,
protected by the Fighting Services, despite the threat from enemy submarines. A
commemoration plaque to this effect was mounted in the main entrance hall of the
power station. A 40 MW set for Congella Power Station at Durban, the
largest set at that time ordered by Escom, was lost at sea in 1943 when the ship
delivering it was sunk by enemy action. Altogether 252 Allied merchant ships
were sunk in the south Atlantic and Cape waters during the war. (Escom Annual Reports 1943:17, 1944:46, 1945:45; Knox-Johnston 1989:82)
The first of the two
Metropolitan Vickers 33 MW sets went into service on 22 January 1945
and the second in April 1945. The first two of the three 33 MW Ljungström
sets and the 7 MW house set ordered from ASEA in 1939 were delivered in
October 1945, soon after war hostilities had ended. The house set was started up
on 10 April 1946 and the two main sets were completed on 1 July and 5 November
1946 respectively. The last ASEA set was delivered in 1946 and commissioned in
March 1947. By the end of 1947 the station-installed capacity was 172 MW
and extensions comprising four additional 33 MW sets, two house sets,
twelve boilers and two cooling towers were on order. (Escom Annual Reports 1945:45, 1946:47, 1947:48)
The second 7 MW house
set was in service at the end of February 1950 and Generator 6 was on load
on 15 February 1951. Special measures were adopted to enable Generator 7
to be placed in service in 1951, but the full output of the seven generators
then installed would not be attained until boilers 11-14 were in service. By the
end of 1952, eight main generators, two house sets and twelve boilers were in
commercial service. At the end of 1953 there were nine main generators, three
house sets, seventeen boilers and four cooling towers in commercial service. The
last boiler was commissioned in 1954 making an ultimate installed plant capacity
of 318 MW. (Escom Annual Reports 1949:52, 1950:46, 1951:89, 1952:89, 1953:89, 1954:91)
A summary of the principal equipment installed is as follows. (Data from Escom Annual Reports)
| Year |
Main Generators |
House Sets |
Boilers |
| 1945 |
2 (axial flow) |
|
6 |
| 1946 |
2 (radial flow) |
1 (radial flow) |
|
| 1947 |
1 (radial flow ) |
|
|
| 1948 |
|
|
|
| 1949 |
|
|
3 |
| 1950 |
|
1 (radial flow) |
1 |
| 1951 |
1 (axial flow) |
|
|
| 1952 |
2 (axial flow) |
|
2 |
| 1953 |
1 (axial flow) |
1 (radial flow) |
5 |
| 1954 |
|
|
1 |
| TOTAL |
9 |
3 |
18 |
Babcock and Wilcox
manufactured the boiler plant. There were 18 units, all fitted with chain grate
stokers. These were the largest link-type stokers in the world. Each unit was
rated at 190 000 lb/h [23,9 kg/s] normal continuous rating. Each
boiler was provided with a separate steel chimney lined with concrete. The
chimney diameter was 8,5 feet [2,6 m] and the height 200 feet [61 m].
The chimneys were anchored to the building structure by means of steel wire
stays. The steam pressure at the boiler superheater outlet was 360 lb/sq.in.
[2,59 MPa (abs)] at a temperature of at 810 °F [432 °C].
The steam conditions at the turbine inlets were 350 lb/sq.in. [2,5 MPa (abs)]
and 800 °F [427 °C]. (Escom Twenty-five Years 1923-1948:46; Escom Golden Jubilee 1923-1973:53;
Escom Annual Report 1980:49; Escom Brochure - Klip, Vaal & Vierfontein Power
Stations)
Each generator transformer
consisted of three single phase units of 13,333 MVA capacity. The voltage
on the generator side was 10,5 kV and on
the secondary side 88 kV. The house sets generated at 3,3 kV. There
were three station transformers each of 8,5 MVA with voltage ratio of
88/3,3 kV. (Escom Twenty-five Years 1923-1948:33; Escom Brochure - Klip, Vaal &
Vierfontein Power Stations)
Capital expenditure during
construction amounted to approximately £10,9 million (as at 31 December
1955). A breakdown of these costs is given below.
| Land and rights |
£ 5 347 |
| Buildings and civil works |
£ 2 357 400 |
| Machinery and plant |
£ 8 517 009 |
| TOTAL |
£ 10 879 756 |
(Escom Annual Report 1955:56)
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| View of the station that appears in Escom Golden Jubilee |
For the first 10 years of its operating life, net electricity production at
Vaal increased steadily to a maximum of 2 195 GWh in the year 1954. For the next
29 years net production averaged about 1 850 GWh. For the closing 6 years
production dropped steadily, and in the final year 1989, auxiliary consumption
exceeded generation. Auxiliary consumption in the station averaged approximately
6% of generation, varying from about 5,5% to 7,5% depending on load factor.
Maximum net power remained consistently close to the sent out rating of 295 MW
for the years 1953 to 1983, reducing during the closing years. (See production
chart)
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| View inside the turbine hall in 1947 showing the radial-flow sets in the foreground and axial-flow sets in the background. Each was rated at 30 MW. |

Maximum net annual production was 2 195 GWh, sent out in the year 1954. Maximum thermal efficiency was 22,9% and was achieved
also in the year 1954. Maximum net power was 301 MW, produced in the year 1955. Statistics for these years, as well as the first
and last full years of production, are given in the table below.
| Year |
Net
Generation
GWh |
Net Max Power MW |
Load Factor (net basis)
% |
Thermal
Efficiency
net basis % |
Coal Consumed metric ton |
Calorific Value of Coal MJ/kg |
Cost of Coal R/metric ton |
| 1946 |
582 |
104 |
63,9 |
22,5 |
430 839 |
21,66 |
0,66 |
| 1954 |
2 195 |
291 |
86,0 |
22,9 |
1 651 345 |
20,89 |
0,75 |
| 1955 |
2 106 |
301 |
79,8 |
22,8 |
1 586 201 |
20,96 |
0,79 |
| 1965 |
2 066 |
291 |
81,0 |
20,9 |
1 799 770 |
19,77 |
1,15 |
| 1975 |
1 793 |
289 |
70,8 |
19,8 |
1 712 010 |
19,08 |
3,22 |
| 1985 |
1 107 |
236 |
46,8 |
17,3 |
1 305 472 |
17,64 |
Not available |
| 1988 |
36 |
92 |
1,7 |
11,2 |
64 994 |
17,46 |
Not available |
Water consumption at the station was 5,4 l/kWh (net) in 1977 and 4,4 l/kWh (net) in 1985.
(Data from Escom Annual Reports-Tables of Power Station Operating Statistics)
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| Commemorative plaque that was displayed in the main entrance hall of the station |
PLEASE
CLICK ON PHOTOGRAPH TO VIEW A LARGER VERSION |
 |
| One of the 7 MW Ljungström house sets built by ASEA of Sweden |
A breakdown of a generator occurred at the beginning of December 1955. As a
precautionary measure the two further machines of the same design were taken out
of service. The cause of the failure was investigated with assistance of the
manufacturers, and it was expected to return the units to service by the winter.
Modifications were made to the three sets and they were returned to service
between July and October 1956. The loss of plant was reflected as a substantial
reduction in the station output for 1956 (see production chart). The loss had to
be made up by increasing loading at the other stations in the pool and in
addition power purchases had to be made from the Municipalities of Johannesburg
and Pretoria. (Escom Annual Reports 1955:54, 1956:51)
The coal used was run-of-mine washed and crushed to minus 3/4 inch [19 mm]
and received by conveyor belt straight from the pithead of the new Cornelia
South Colliery. The calorific value was over 21 MJ/kg for the first 8
years, dropping to below 20 MJ/kg by 1960, below 19 MJ/kg by 1973 and
below 18 MJ/kg in 1985. The station was not adversely affected by the
Coalbrook mining disaster in 1960. The Cornelia Colliery, belonging to the
Anglo-American Corporation, was later extended and re-named New Vaal Colliery to
supply Lethabo Power Station as an open-cast mine with coal as low as 15 MJ/kg
in calorific value. Lethabo was built 3½ km northeast of Vaal Power
Station and the first set there was commissioned in December 1985. (Escom
Twenty-five Years 1923-1948:46; Escom Annual Reports-Tables of Power Station
Operating Statistics; Escom Megawatt No.65/April 1981:6; Eskom News July
2003:32)
The ash handling plant comprised a system of high velocity water sluiceways,
ash and water sumps, telpher grabs and ash bins. From these bins the ash was
transferred into the buckets of the aerial ropeways for conveyance to the dumps.
The total amount of coal consumed over the 44-year life span of the station
amounted to 62 million metric tons. With an ash content of approximately 25%,
the ash dumps grew to a considerable size. After closure of the station the ash
dumps were taken over by Roshcon, a division of Eskom Enterprises. The ash is to
be used for the making of building bricks. (Simunye Decommissioning 2004)
In 1945, negotiations started that lead to the expropriation of the VFP and
the purchase by Escom of its assets. This took place on 1 July 1948. Vaal
Power Station had always been owned by Escom, but had been operated by the VFP
on behalf of Escom. The VFP staff members were transferred to its subsidiary,
the Rand Mines Power Supply Company, up to 31 December 1948. From 1 January
1949 they were formally transferred to Escom. During the early 1980's the staff
complement consisted of 858 employees. At closure of the power station in 1989,
the staff members were either transferred to other stations or took retirement.
(Escom Golden Jubilee 1923-1973:21; Escom Brochure - Klip, Vaal &
Vierfontein Power Stations)
During the 1980's Eskom had been commissioning its new giant six-pack power
stations. But due to a decrease in the rate of growth in the demand for
electricity, Eskom began to experience a surplus of generation capacity. The
older and less efficient stations were thus no longer required. Vaal Power
Station was closed down in 1989, having reached the end of its economic life. (Escom
Annual Report 1989:24; Conradie and Messerschmidt 2000:259-260)
An agreement was concluded with United Carbon Producers (Pty) Ltd in August
1990 whereby United Carbons would utilise certain facilities at the power
station for the purpose of producing smoke-less fuels for domestic use and char
for industrial use. The boilers would be modified for use as furnaces. Certain
other plant and equipment, buildings, housing and adjacent land were to be
leased for a period of 15 years. (Eskom News No.154/16 Oct 1990:3
The four cooling towers were demolished in July 1996 by means of explosives.
These were the tallest structures in South Africa when they were built, but were
sadly reduced to rubble within seconds when they were demolished. (Eskom News
August 1996:3)
The smoke-less fuel project was not a financial success. After 1998 the plant
was sold as scrap, the power station buildings totally demolished, and the land
rehabilitated. The township has now been taken over and is being administered by
the staff at Lethabo Power Station. The pumping station at the Vaal River has
also been taken over by Lethabo. (Simunye Decommissioning 2004)
- A History of Technology (Edited by Trevor L Williams) Volume VII
- Clarendon Press - Oxford, 1978
- Auger, CP - Engineering Eponyms - The Library Association - Staples
Printers Ltd, Kent, England, 1965
- Conradie SR and Messerschmidt LJM: A Symphony of Power - The Eskom
Story - Chris van Rensburg Publications (Pty) Ltd, Johannesburg, 2000
- de Villiers I: The development of the Electricity Supply Commission in
the post-war years. In: The Transactions of the South African Institute of
Electrical Engineers, February 1957 (Presidential Address)
- Electricity Supply Commission: Annual Reports, 1948-1984
- Escom Brochure - Klip, Vaal & Vierfontein Power Stations (approx
1981)
- Escom: Golden Jubilee 1923-1973
- Escom: Megawatt 1966-1981
- Escom News / Eskom News
- Eskom: Statistical Yearbooks, 1985-1990
- Hanks P & Hodges F: A Dictionary of Surnames - Oxford University
Press, 1988
- Knox-Johnston R: The Cape of Good Hope - A Maritime History - Hodder
& Stoughton, London, 1989
- Ljungström Dr F: The Development of the Ljungström Steam Turbine and
Air Preheater. In: Institution of Mechanical Engineers (London),
Proceedings, Vol 160, September 1949 (pages 211-223)
- McGraw-Hill Dictionary of Engineering, Fifth Edition - New York, 1997
- Reay Dr DB: Some mechanical advances in the power station practice of
the Electricity Supply Commission. In: The Certificated Engineer, June 1961
- The South African Engineer and Electrical Review - February 1945
- Troost Dr N and Norman HB: Electricity Supply in South Africa. In: The
Transactions of the South African Institute of Electrical Engineers,
September 1969
[ OVERVIEW I BACKGROUND I CONSTRUCTION I OPERATION AND PRODUCTION I MAJOR
BREAKDOWNS I COAL SUPPLIES I ASH DISPOSAL I STAFF I CLOSURE AND DEMOLITION I BIBLIOGRAPHY ]
|
| This webpage was last
updated on 25 January, 2007 |
|