
[BRIEF HISTORY I DATES ON WHICH THE
UNITS WENT INTO COMMERCIAL SERVICES I POWER
STATION MANAGERS I DUVHA &
ITS INVOLVEMENT IN THE COMMUNITY I INTERESTING
EVENTS I BRIEF DESCRIPTION OF
THE PLANT I TECHNICAL DATA ]
BRIEF
HISTORY
During the seventies the
demand for electricity in South Africa increased at an average of nine percent per year.
In response to this demand, Dr Straszacker the chairman said, Escom had to virtually
double its generating capacity. Against this background, construction of Duvha power
station started in November 1975 on a farm called Speekfontein just outside Witbank. Duvha
was one of South Africas largest fossil fired power stations, and was often referred
to as the "flagship" of the Eskom fleet. The combined generating capacity of the
six units is 3 600 MW, enough power to supply a city three times the size of Johannesburg
with electricity on a winters night. Duvha is a base load plant. This means it
operates around the clock to help meet South Africas electricity requirements. The
demand for Duvhas electricity is determined by the National Control Centre,
according to system requirements, plant availability and other strategic factors. The
availability of coal and water makes this area ideally suited for the establishment of
power stations. Hence, this region is better known as the Power House of South Africa.
When Duvha was completed the smoke stacks were the tallest freestanding concrete
structures in the Southern Hemisphere each 300 metres tall (July 1992). Margaret Rawics
was responsible for the landscape planning and design of the site.
Mpumalanga, previously
known as Eastern Transvaal, means "Where the sun rises" Symbolically Duvha, the
Venda word for the sun, can be seen as the heart of this region and is not only generating
electricity, but indicates light to the people of this country. Duvha power
station ascribes to the Eskom vision to "provide the lowest-cost electricity the
world for growth and prosperity and fully support the Eskom Generation priorities.
DATES ON WHICH THE UNITS WENT INTO COMMERCIAL SERVICE
Unit 1 went into commercial
service on 18 August 1980, Unit 2 on 1 October 1980, Unit 3 on 16 September 1981, Unit 4
on 1 July 1982, Unit 5 on 31 March 1983 and Unit 6 on 22 February 1984. Project costs
totaled T1,6 billion over that eight-year period. Something significant about these dates
is that the planned commercial loads were to be 12 months apart, but due to demand the
interval between units four and five was reduced to nine months, which in itself was an
achievement.

Last unit still under construction

Early stages of construction
|
The last of
Duvhas six 600 MW units were taken into commercial operation in February 1984.
Project costs totalled R1,6 billion over that eight-year period.
POWER STATION MANAGERS
Duvha has had six Power
Station Managers to date namely: Don Burger , Ross Hatton, Colin Marsh, Louis Nel, Ehud
Matya (the first black power station manager in Eskom) and Brian Dames to date.

Ehud Matya the first black power station
manager
in Eskom

General view of Duvha power station
|
DUVHA AND ITS INVOLVEMENT IN THE
COMMUNITY
Duvha is involved in the
education of children from the area by providing assistance to the Duvha Primary School
and Hanga Secondary School located near the power station.
Duvha Primary School was
established in 1982 with the power station developing available facilities.
In 1992 Hanga Secondary
School also opened its doors. Duvha continued to support these schools largely
towards transportation of school children.
Duvha also contributed to
the development of small businesses and therefore supported job creation and economic
growth. Facilities at the Ikagne single quarters were converted into little shops.
Identified entrepreneurs were empowered to run their businesses and currently there is a
total of six shops, a shoe repair and leather workshop, a general dealer, welding shop, a
tailor, a dressmaker and a dry cleaning service
Integration with the local
community was one of the 1996 goals and several interventions took place of which one was
a clean up day at four schools in Witbank.
INTERESTING
EVENTS
In Duvhas short
history it has experienced many interesting events.
The Duvha AmaZulu dancers
attended an international Eistedford in France in July 1989. If you have ever watched the
AmaZulus dancing, you will recall how captivating the dance is. As they pound their
drums and rustle their animal skins, one is drawn closer to their history. The Duvha
AmaZulus have performed at many other popular venues such as Gold Reef City, the CSIR and
at various shows. It was the team spirit and enthusiasm that motivated their trip to
France it was with great pleasure that Duvha sent these men to France to be, not
only ambassadors for Eskom, but South Africa at large.
In 1986 a baboon got past
the security gates in a very mysterious way. A security guard spotted the baboon first.
The baboon very calmly, walked to the gate and the security guards couldnt believe
their eyes. This created a fair amount of chaos as the baboon was chased. After searching
for a day the baboon was found trapped between unit 5 and 6. The inevitable had happed
since the baboon was dangerous and bewildered. To this day his origin is still unknown.
Another interesting event
at Duvha occurred in 1988 when Protective Services personnel found a big mole snake at the
gate. They caught the snake and another employee, who was doing research on mole snakes,
let it fee in safer surroundings.
BRIEF
DESCRIPTION OF THE PLANT

View of the interior of the control room
CONTROL
Each of Duvhas six boiler-turbine sets is run as a separate entity, with
its own controls and instrumentation incorporated into its own control desks and panels.
There are three control rooms, each serving a pair of sets. Here the operators can
execute every major task associated with start-up, normal operation, shutdown and
emergency operation. The operators are in permanent contact with other Eskom control
centres that make up the integrated transmission network. A data-logging computer
continuously monitors the main operating and alarm systems, and provides a constant flow
of information on video screens and printers. |
COAL
SUPPLY
Crushed coal, smaller than 25 mm is delivered from the neighbouring Duvha Opencast
Mine, the largest opencast coal mine in the Southern Hemisphere. Duvhas opencast
mine was started in 1976, and is now capable of supplying just over 10 million tons of
coal a year. Reserves will last for more than 30 years at that rate of production. A 4,5
km conveyor belt to form a single energy unit links the power station and the colliery.
Delivery to the plant is at the rate of 845 000 tons a month, and the two staithes have
capacities of 55 000 and 110 000 tons respectively. In addition a stockpile of 500 000
tons is maintained. From the staiths, coal is fed to the boiler bunkers, of which there
are six per boiler. Each bunker has a capacity of 670 tons, which means there is
sufficient storage capacity at the boilers for 12 hours operation at full load. When a
furnace is started up, fuel oil is used until the combustion of the pulverised coal is
stable. At Duvha, two storage tanks are used for fuel oil, with a combined capacity of 3
000 tons.
Following on behind the
strip mining, the spoil piles are flattened, covered in topsoil and fertilised, and then
replanted with various types of grass, trees and shrubs. A nursery has been established
for the restoration programme.
A project has been
established whereby the life of the coal reserves for use by Duvha power station has been
extended to ± 40 years. The project entails the washing and blending of coal obtained
from three different mines namely: Douglas, Middelburg and Wolwekrans.
Long term benefits of this
project include the utilization of coal reserves from these mines as well as a consistent
supply of a better quality blended coal to the power station. A new coal sampling plant
was commissioned before the commencement of the new coal supply agreement between Eskom
and Ingwe early in 1995.

A draglinne excavatot at the open cast mine at
Duhva power station

View from the HV yard
|
MILLS
Coal from the boiler bunkers is fed under control into the mills, the feed rate being
determined by the requirements for steam. Inside the mills either large steel balls or
rollers run in circular tracks, to pulverise the coal to powder. This fine, highly
combustible powder is blown from each mill into the boilers at some 63 tons an hour. There
are six mills to each boiler, providing a spare capacity of two mills per boiler when coal
of design quality is being burned. At full capacity, each boiler requires between 250 and
300 tons of coal an hour, depending on the calorific value of the coal.

Coal mill at Duvha power station

General view of Duvha power station
|
BOILERS
The six boilers are of the Benson type, which depends on forced circulation and has no
steam drum. The feedwater, which is highly purified and demineralised, makes one
continuous and uninterrupted circuit through boiler, turbine, condenser, and boiler again.
On its path through the boiler, the feedwater evaporates and as more heat is absorbed, the
steam becomes superheated to a temperature of 540° C and a pressure of 17,1 MPa.

View of a boiler under construction
|
A feature of
the steam pipework is a high-pressure system that allows the superheated steam to bypass
the high-pressure turbine when necessary, to flow directly into the reheat pipe work. From
there, it bypasses the intermediate pressure and low pressure turbines and flows into the
main condenser. This system means that the boiler can be operated independently of the
turbine and the correct steam temperature and pressure can be obtained before the
generator is started up. Also, if a turbine trips, the system allows the boiler to be
operated at roughly 40 per cent of its maximum load, ready for a rapid restart; and, if a
turbine sheds a large part of its load, the turbine can be run at a low load while the
boiler is maintained at a higher load. In both instances, the boiler is maintained at a
higher load. In both instances, the bypass system prevents, within the limits of its
capacity, sudden pressure rises from exceeding the settings of the safety valves in the
re-heater.
Each boiler is fitted with
24 burners arranged in six rows of two in each of the front and rear walls of the furnace.
Each coal mill supplies four burners two in the front wall and tow in the rear
wall. Mounted in the centre of each burner is an oil burner, and these are used for
starting up and for stabilising the combustion of coal at low loads.
Forced draught fans supply
secondary air to the burner windboxes while primary air fans transport pulverised coal
from the mills to the burners. Combustion gases are drawn from the furnace, by two induced
draught fans, over the surfaces of the steam superheater, the re-heaters, the economiser,
and air preheaters, through the electrostatic precipitators and into the chimney. The
precipitators collect more than 99 per cent of the dust, or fly ash.
Each boiler has a capacity
of 507 kg/s of steam, and the feedwater is supplied, at a pressure of 22 Mpa, by two
electric pumps rated at 13 MW each or one steam-driven pump. At maximum continuous rating
the efficiency of the boilers is 93,9 per cent. The total mass of one boiler and its
supporting structure is 9 800 tons, and its water content, when cold, is 185 tons. The
volume of the furnace is approximately 13 000 m².
Fabric Filter
Plants (Unit 1,2 and 3).
This plant replaces the precipitators for Units 1,2 and 3 and consists of an ABB fläkt
Optipulse pulsejet fabric filter, utilising acrylic dralon T bags. The filter is divided
into four isolatable compartments. Each compartment contains a total of 6 724 bags, each
eight metres long, giving a total of 26 896 bags per boiler. The plant is designed to
handle 1 290 cubic metres of boiler gas per second, which gives a filter velocity of
90,015 metres/sec.
TURBINES
There are six turbines at Duvha power station, manufactured by GEC Turbo-Generators of
Rugby in the United Kingdom. Each turbine unit has high-pressure and intermediate pressure
cylinders and twin double-flow low-pressure cylinders. The high pressure and intermediate
pressure cylinders are constructed with an internal and external casing to allow for fast
starting up and rapid variation in load. Foundations and supports for one turbine include
8 000 m³ or 20 000 tons of concrete.

A Turbo Alterntor Set at Duvha power station

A view of a Turbo Alternator set under construction
|
FEED HEATING PLANT
The condensate temperature in the condenser hotwell is about 37°C. In order to obtain
maximum system efficiency it is necessary to reheat the condensate before returning it to
the boiler. To achieve this, the condensate is passed through numerous heaters before
feeding it into the boiler. All the heaters are of the surface type in which the water
flows through tube nests. Steam extracted from different stages of the turbine heats the
water by conduction through the tube metal.
A de-aerator, situated
between the low- and high-pressure heaters, removes entrained oxygen in the condenstate
and heats the water through direct contact with steam extracted from the turbines. The
condenstate is pumped from the condenser to the deaerator through the low-pressure heaters
by means of the main condensate extraction pumps. The condensate is then pumped from the
de-aerator feedwater tank to the boiler through the high-pressure heaters by the boiler
feedpumps. The final feedwater temperature at 600 MW is 247ºC.
CONDENSERS
The condensers are of the dual-pressure, surface type. The vacuum inside the condensers is
established by steamjet air ejectors and maintained in normal operation by waterjet air
ejectors. The steam exhausted from the low-pressure cylinder condenses over 22 552 brass
tubes, which have a surface area totalling 23 400m². Each boiler-turbine set has a
condenser with a heat exchange capacity of approximately 400 MW.
GENERATORS
Each generator is rated at 667 MVA, and produces 600 MW at full load. The sent-out
capacity is 575 MW, the difference of 25 MW being used to run the auxiliary equipment of
the turbine and boiler plant. Generator cooling is achieved through two systems. The
stator and rotor are cooled by hydrogen at a pressure of 400kPa, which is circulated
through water coolers of the surface type. Circulation of the hydrogen is by two fans that
are locked to the rotor shaft. The circulation of demineralised water-cools the stator
windings and core. The generators operate at 22 kV, and their output is transformed to 400
kV for distribution via the national grid.
CHIMNEYS
Duvhas two chimneys are the tallest freestanding concrete structures in the Southern
Hemisphere, at 300 m each. Each chimney contains three flues, so that there is one flue
per boiler. The diameter of the chimneys at the base is 22m, and both are on 60 piles of
1,2 m by 18m. Approximately 40 000 tons of concrete was used in the construction of each
stack.
COOLING TOWERS
The six cooling towers at Duvha are designed for a total thermal load of nearly 19 000
GJ/h. The three larger towers are 149 m in height and 114 m in diameter at the base. The
minimum shell thickness is 180 mm. At full load, the evaporation from one tower amounts to
30 Ml a day.
WATER SUPPLY
Duvhas water requirements can be met from either of two sources. First, water can be
pumped from the Vygeboom and Nooitgedacht Dams in Mpumalanga, which are fed by the Komati
River. These dams can also be supplied with water from the Usutu system. Secondly, water
can be obtained from the Witbank Dam in the upper reaches of the Olifants River and
supplemented with water from the Grootdraai Dam in the Vaal River near Standerton.
The second source is used
as little as possible because it is not as clean as the Komati River. Clean water is
highly desirable, since purification and demineralisation costs are proportional to the
concentration of material that has to be removed. This second source is only used if the
Komati system cannot supply the water.
| TECHNICAL
DATA |
|
| Generating capacity |
3600 MW |
| Operating |
3 shifts of 70 in 24 hours |
FUEL |
|
| Mining company |
Ingwe Group |
| Calorific value |
23,32 MJ/kg (dry basis) |
| Ash content |
28,85 per cent (dry basis) |
|
|
| TECHNICAL DATA |
|
| Generating capacity |
3600 MW |
| Operating |
3 shifts of 70 in 24 hours |
| FUEL |
|
| Mining company |
Ingwe Group |
| Calorific value |
23,32 MJ/kg (dry basis) |
| Ash content |
28,85 per cent (dry basis) |
| Total annual consumption |
10 135 000 tons |
Coal staithe capacity
No 1
No 2 |
110 000 tons
55 000 tons |
| Boiler bunker capacity |
24 120 tons |
| Coal consumed at full load |
1 500-1 800 tons per hour |
| MILLING PLANT
Sets 1-4 |
|
| Manufacturer |
Babcock & Willcox (SA) |
| Type |
Vertical spindle (ball & ring) |
| Number |
6 per boiler |
| Speed |
26 r/min |
| Rated output |
66 tons/hour |
| Sets 5 and 6 |
|
| Manufacturer |
Loesche |
| Type |
Vertical spindle (roller type) |
| Number |
6 per boiler |
| Speed |
36 r/min |
| Rated output |
66 tons/hour |
| BOILERS |
|
| Manufacturer |
SteinMüller(Africa)(Pty)Ltd |
| Type |
Benson |
| Number |
6 |
| Maximum continuous rating |
17,1 MPa |
| Final steam teperature |
540oC |
| Reheater steam pressure |
39,1 MPa |
| Reheater steam temperature |
540oC |
| Number of burners |
24 |
| Height (roof of hopper) |
94,0 m |
| Width at burner level |
20,2 m |
| Depth at buner level |
17,2 m |
| Boiler expansion (downwards) |
340 mm |
| Approximate volume |
13 080 m3 |
| BAG FILTERS (Unit 1,2 and 3) |
|
| Manufacturer |
ABB Power Tech |
| Control temperature inlet |
126,5oC max & 120oC
min |
| Differential Pressure |
2,3 kPa |
| Filter velocity |
0,015 m/sec |
| System control |
Siemens S135 PLC |
| Effective cloth area |
86 170 m2 |
| Stack emission |
50 mg/sm3 |
| ELECTROSTATIC PRECIPITATORS |
|
| Manufacturer |
Lurgi SA |
| Control gas temperature |
150oC |
| Operating volume |
2 000 0 0 m3/h |
| CO2 content |
41 mbar |
| Gas dust load (inlet) |
30 g/m3 |
| Clean gas dust load |
120 mg/m3 |
| TURBINES |
|
| Manufacturer |
GEC Turbine Generators(Pty) Ltd |
| Type |
Multi-cylinder impulse-reaction |
| Rating (Generator output) |
600 MW |
| Speed |
3000 r/min |
Superheated steam pressure,
HP stopvalve inlet |
16,1 MPa (abs) |
Superheated steam temperature,
HP stopvalve inlet |
535oC |
| Steam pressure, HP outlet |
4 MPa (abs) |
| Steam temperature, HP outlet |
332oC |
| Reheated steam pressure, IP inlet |
3,75 MPa (abs) |
Reheated steam temperature,
IP inlet |
535oC |
| Steam pressure, IP outlet |
0,42 MPa (abs) |
| Steam temperature, IP outlet |
252oC |
| Steam pressure inside condenser |
8 kPa (abs) |
| Average teperature inside condenser |
37oC |
| Heat consumption (MCR) |
8 220 KJ/kWh |
| Steam Flow |
520 kg/s |
| GENERATORS |
|
| Manufacturer |
GEC Turbine Generators(Pty) Ltd |
| Rated capacity |
600 MW (maximum continuous output) |
| Terminal voltage |
22 kV (50 Hz) |
| Power factor |
0,9 (lagging) |
| Cooling medium |
Hydrogen at 400 kPa |
| GENERATOR-TRANSFORMERS |
|
| Manufacturer |
ASEA Electric (SA) Ltd |
| Rated capacity |
700 MVA |
| Terminal voltage: Primary |
22 kV |
| Terminal voltage: Secondary |
420 Kv |
| COOLING TOWERS |
|
| Number |
6 |
| Type |
Hyperbolic natural draught |
| Overall dimensions |
Sets
1-3 Sets 4-6 |
| Height |
180
mm 180 mm |
| Nominal flow rate/ct |
45 000 m3/h
48 800 m3/h |
| Temperature-in |
39,44oC
34,7oC |
| Temperature-out |
22,5oC
19,2oC |
| Evaporation at duty point |
1 270 m3/h
1 270 m3/h |
| Nominal heat rejection |
886
MW 886 MW |
Maximum guaranteed heat
Rejection |
1 275
MW 1 275 MW |
| Number |
12 |
| Total capacity |
78 m3/s |
| CHIMNEYS |
|
| Number (3 flues each) |
2 |
| Height |
300 m |
| Wundshield diameter (base) |
22 m |
| MAIN CONTRACTORS |
|
| Earthworks |
Grinaker Construction (Pty) Ltd |
| Civil Engineering |
LTA Construction |
| Steelwork (subcontractor) |
Dorbyl Ltd |
| Boilers |
Steinmuller (Africa) (Pty) Ltd |
| Turbines |
GEC Turbine Generators (Pty) Ltd |
| Generator transformers |
ASEA Electric (SA) Ltd |
| Cooling towers |
Hamon Sobelco
(with LTA Construction
as civil subcontractor) |
| Chimney 1 |
Monanhan and Frost (Pty) Ltd |
| Chimney 2 |
Murray and Roberts (Transvaal) (Pty) (Ltd) |
| Cabling |
Huberts Davies (Pty) Ltd |
| Instrumentation |
Siemens Ltd |
| Process computers |
Honeywell |
| Fire Control System |
Mather and Platt (Pty) Ltd |
| Coal handling (staithes) |
High Structures (Pty) Ltd |
| Conveyers |
Spencer Melksham (Pty) Ltd |
| Ash Plants 1-3 |
DB Thermal |
| Ash Plants 4-6 |
Steinmuller Africa (Pty) Ltd |
| Construction water ring |
Hall Longmore & Company |
| Cooling water pumps 1-3 |
Amalgamated Power Engineering
(SA) (Pty) Ltd |
| Cooling water pumps 4-6 |
Sulzer Bros. (SA) Ltd |
| Sewage plant |
Satec Hudamec |
Fabric filer
Plants 1-3 |
ABB |
| Electrostatic precipitators |
Lurgi (SA) (Pty) Ltd |
| Water treatment plant |
Foster Wheeler |
| Bibliography
Duvha Coal-fired giant - Technical
information Brochure
Eskom News
Megawatt Magazines
Escom Annual reports
Duvha internal Newsletter |
Interviews
Martinus Biemons
Technical Support Services Manager
Duvha Power Station |
[ BRIEF HISTORY I DATES ON WHICH THE
UNITS WENT INTO COMMERCIAL SERVICES I POWER
STATION MANAGERS I DUVHA &
ITS INVOLVEMENT IN THE COMMUNITY I INTERESTING
EVENTS I BRIEF DESCRIPTION OF
THE PLANT I TECHNICAL DATA ]
|
| This webpage was last
updated on the 07 November, 2003 |
|